On July 16, 2020, the Federal Energy Regulatory Commission (“FERC” or “Commission”) dismissed a petition filed by the New England Ratepayers Association (“NERA”) requesting that the Commission declare that certain sales of energy by net-metered, behind-the-meter generators are exclusively subject to federal jurisdiction. If granted, the petition would have resulted in the rates for such sales being set at an avoided cost rate in accordance with the Public Utility Regulatory Policies Act of 1978 (“PURPA”) or wholesale market prices under the Federal Power Act (“FPA”), as applicable, rather than the interconnected utility’s retail rate. The Commission declined to address the legal issues raised by the petition. Instead, it determined that the issues presented in NERA’s petition do not warrant a generic statement from the Commission at this time because NERA failed to identify a specific controversy or harm that the Commission should address. However, concurring opinions from two commissioners suggest that future fights may be imminent over the scope of FERC’s authority to regulate net metering transactions and the rates for such transactions.
Continue Reading FERC Rejects Net Metering Petition, But Fight Is Far From Over
FERC Proposes Major Changes to PURPA Regulations Impacting Qualifying Facility Rates and Requirements; Throwing Roadblocks in the Path of Renewable Energy Development
The Federal Energy Regulatory Commission (“FERC”) requested comments on a proposed rulemaking to revise its regulations under the Public Utility Regulatory Policies Act of 1978 (“PURPA”). The Notice of Proposed Rulemaking (“NOPR”), among other things, would diminish benefits that have been afforded to Qualifying Facilities (“QFs”), including the availability and value of the “PURPA-put.” The proposed changes also could potentially block certain wind and solar projects that previously would have qualified as small power production facilities from receiving that designation. The NOPR presents uncertainty for renewable developers, as well as other non-utility generators. Adoption of the proposed changes may hinder the development of some renewable energy projects. Comments on the proposed rulemaking are due within 60 days of its publication in the Federal Register.
Continue Reading FERC Proposes Major Changes to PURPA Regulations Impacting Qualifying Facility Rates and Requirements; Throwing Roadblocks in the Path of Renewable Energy Development
9th Circuit Says CPUC’s Standard Contract and Re-MAT Program for Certain Renewable Generators are not PURPA Compliant
In a recent opinion, the Ninth Circuit held that the California Public Utilities Commission’s (CPUC) Renewable Market Adjusting Tariff (Re-MAT) program and alternative Qualifying Facility (QF) standard offer contract (Standard Contract) were preempted by federal law. The Re-MAT program and Standard Contract required California utilities to purchase energy from certain QFs with capacities up to three and twenty megawatts (MWs), respectively. The court found that the program and the contract violated the Public Utility Regulatory Policies Act of 1978’s (PURPA) pricing requirements. The decision, Winding Creek Solar LLC v. Peterman, USCA Case Nos. 17-17531 and 17-17532 (9th Cir. 2019) demonstrates that PURPA continues to maintain a floor from which state regulatory programs must encourage the development of renewable energy from small producers. In 2018 and prior to Winding Creek, the CPUC instituted a rulemaking to consider adoption of a new Standard Contract but has not yet taken action. Winding Creek reemphasizes the importance of that proceeding for ensuring that California has a PURPA-compliant program in place for utilities to purchase QF-produced energy.
Continue Reading 9th Circuit Says CPUC’s Standard Contract and Re-MAT Program for Certain Renewable Generators are not PURPA Compliant